Mae Richardson Elementary

Overview

Project Summary: Mechanical, Electrical, Plumbing and Site Upgrades

Campus buildings will receive new heating, ventilation and air condition (HVAC) systems, electrical systems, and plumbing. New HVAC systems will create a comfortable learning environment with state-of-the-art indoor air quality by using appropriate filters and code-mandated air changes. A new digital HVAC control system will efficiently “warm up” buildings to a desired temperature on cold morning prior to staff and students arriving, and will “turn down” the heat when it knows or senses the buildings are empty. These controls will create thermally comfortable spaces and allow district maintenance staff to control mechanical systems remotely if necessary.

The existing gravel parking lot will be paved and reconfigured to create safer student drop-off and pick-up, and storm drain issues will be addressed. School-wide security systems will be upgraded or installed to include new fencing around the core of the school buildings, security cameras, an intercom system, classroom clocks and fire alarm panels. New exterior and classroom door hardware will have already been installed under another project.

Bond Goals Addressed

  • IMPROVE MECHANICAL SYSTEMS FOR EFFICIENCY AND HEALTH
  • IMPROVE SAFETY AND SECURITY

Estimated Project Cost: $5.2M

Project Updates

Winter 2024 Updates:

  • New security fencing is now complete.
  • The D6 Board has awarded SB James with the contract to design the new gymnasium at Mae Richardson Elementary. Stay tuned for more progress updates on the new gym design.

Recent updates:

  • Screening around HVAC Units on roof has been installed
  • New intercom system is complete
  • New paved parking lot finalized (see below photo)

Mae Richardson parking lot remodel is complete!

Upgrades and updates to building systems are in full swing this summer. Improvements including Mechanical, Electrical, and Plumbing system upgrades/replacement as well as a new air conditioning/indoor air quality system

mae
  • Project Manager: Otak CPM Portland/Medford
  • Architect: BBT Architecture (Bend)
  • Engineer: ArcSine Engineering (Medford)
  • General Contractor: S&B James Construction (White City)
  • Principal/School Contact Information: Katrina Douglas
  • District Contact Information: Spencer Davenport, Chief Projects Officer
  • General Information: 541-494-6202, bond.projects@district6.org

Schedule

2020 2021
J F M A M J J A S O N D J F M A M J J A S O N D
Design
Construction
Owner Prep and Move-in