Project Summary: Mechanical, Electrical, Plumbing and Site Upgrades

Campus buildings will receive new heating, ventilation and air condition (HVAC) systems, electrical systems, and plumbing. New HVAC systems will create a comfortable learning environment with state-of-the-art indoor air quality by using appropriate filters and code-mandated air changes. A new digital HVAC control system will efficiently “warm up” buildings to a desired temperature on cold morning prior to staff and students arriving, and will “turn down” the heat when it knows or senses the buildings are empty. These controls will create thermally comfortable spaces and allow district maintenance staff to control mechanical systems remotely if necessary.

School-wide security systems will be upgraded or installed to include new fencing around the core of the school buildings, security cameras, an intercom system, classroom clocks and fire alarm panels. New exterior and classroom door hardware will have already been installed under another project.

Bond Goals Addressed

  • IMPROVE MECHANICAL SYSTEMS FOR EFFICIENCY AND HEALTH
  • IMPROVE SAFETY AND SECURITY

Estimated Project Cost: $3.7M

Project Updates

 

  • HVAC installation is complete
  • New fencing for campus security is complete
  • New intercom has been installed
  • New boiler equipment has been installed

Final installation of HVAC units on the roof of Patrick Elementary
New HVAC units installed on the roof of Patrick Elementary

Upgrades and updates to building systems are in full swing this summer. Improvements including Mechanical, Electrical, and Plumbing system upgrades/replacement as well as a new air conditioning/indoor air quality system

patrick
  • Project Manager: Otak CPM Portland/Medford
  • Architect: BBT Architecture (Bend)
  • Engineer: Sazan Engineering (Portland)
  • General Contractor: Vitus Construction (Gold Hill)
  • Principal/School Contact Information: Michelle Cook
  • District Contact Information: Spencer Davenport, Chief Projects Officer
  • General Information: 541-494-6202, bond.projects@district6.org

Schedule

2020 2021
J F M A M J J A S O N D J F M A M J J A S O N D
Design
Construction
Owner Prep and Move-in